top of page

Skill: Dig in Cables/Duct and Make Good with Tarmac, Pavers, and Gravel

Skill level: 2

Gate Mechanics

Learning Objective
Understand how to safely and professionally dig in duct or cable, and make good with the appropriate finish (tarmac, paving, gravel) to ensure functionality, safety, and a tidy final appearance. This is mainly for new mains cables. You may need a machine for longer runs.

1. Overview

Poorly installed cable runs can cause:

  • Trip hazards or vehicle damage

  • Damage to buried services

  • Water ingress into ducting

  • Customer complaints due to untidy finishes or delays

✅ Your aim is a clean, secure, and professional job that lasts — and doesn’t need fixing later.

2. Tools & Materials Required

  • CAT scanner

  • Insulated digging tools

  • Maybe trenching machine

  • Maybe mini digger

  • Ducting (usually 40mm or 63mm)

  • Electrical warning tape

  • Tarmac (20mm)

  • Concrete (for duct bedding)

  • Playpit sand (for paving)

  • Soft-faced mallet

  • Tarp or sheeting

  • Blowtorch (for softening tarmac)

  • Rake, broom, gloves, torch

3. Before You Start

  • Confirm cable/duct route with customer and co-workers (see other lesson)

  • Use a CAT scanner to avoid underground services.

  • Check weather forecast — avoid digging in heavy rain.

  • Plan where to put spoil — bring tarps or buckets.

  • Ensure correct tools and materials are on site (pavers, tarmac, sand, barriers).

  • Ask: Will access be needed over the trench soon?

  • Decide if a trencing machine, mini digger or manual excavation is most ecconimical. A trenching machine will not work at all well on anything other than clean soil, a mini digger is good for any ground but makes a big mess, hand digging is ok up to about 20m but 1-2 man days is the maximum before machine hire becomes a better option. Even if it costs a little more.

4. Procedure (Main Process)

A. Prepare and Dig

  • Confirm route, scan with CAT.

  • Mark dig line and check for obstructions.

  • Brush gravel back to one side far enough away not to mix with the spoil.

  • Cut and remove or roll up turf carefully if present.

  • Dig trench to required depth (typically 300–600mm).

  • Place spoil on tarps, not directly on surfaces.

  • Lay duct or cable, include warning tape 100mm above cable.

  • Keep min 50mm separation mains from data cables.

B. Backfill

  • Consider backfilling the same day or even as you go if appropriate. If you have a spare person and the ground is soft they can lay the cable, dig tape and back fill by hand behind you.

  • Use soft sand around cable or duct as needed.

  • Compact gently as you go to avoid later sinkage.

  • Leave room for finish layer.

  • Bulking up usually settles back down to it original volume after some time.

C. Reinstatement by Surface Type

  • Pavers: Ensure compacted base is level. Replace pavers, tapping gently with a soft mallet. Fill joints with playpit sand and sweep thoroughly.

  • Tarmac: Concrete around duct if required. Place and compact tarmac while warm. Use a blowtorch to soften cold tarmac for compaction or use tarmac that is preheated. Slightly overfill — it will settle.

  • Gravel: Rake back evenly. Compact sub-layer beneath if disturbed. Add matching gravel for a neat finish.

  • Turf: Place turf back over the trench, don't worry if it's standing a bit proud it will settle and patches of missing grass will recover quickly.


5. Best Practices

  • Photograph trenches and reinstatement for records.

  • Label duct routes in Clik/job notes.

  • Keep trench lines as short and direct as possible.

  • Use barriers/signs if trench must be left open temporarily.

  • Ensure reinstated finish matches surrounding area.

6. Common Mistakes to Avoid

🚫 Forgetting to CAT scan = service strike
🚫 Leaving spoil scattered or turf upturned
🚫 Failing to concrete around ducts = future subsidence
🚫 Laying pavers on poor base = loose/rocking finish
🚫 No warning tape = no future warning
🚫 Leaving surface below finish level = visible dip later


7. Safety References

Refer to:

  • SSOW-09: Safe Use of Cable Avoidance Tools

  • SSOW-01: General Site Safety

  • SSOW-04: Excavation and Groundwork Safety 

before starting duct/cable digging works.

Copyright Fort Knox Security Ltd 2025
bottom of page